Grafton Public Library

Library Updates

Weekly Report Nov 16-20

Posted by on

Jan Parise has submitted her retirement. She began as a temporary employee and was hired in 2012 to work part-time at the Circulation Desk, where in addition to direct patron service she facilitated the museum pass program and assisted with requests for materials outside of the C/W MARS network. Her last day is Friday December 9 – we wish her well!

Grafton High School Yearbooks from 2014-2019 have been digitized courtesy of Grafton Public Schools, Grafton Public Library, Boston Public Library and the Digital Commonwealth. To reminisce and view scanned yearbooks from 1940 and 1952-2019, please go to https://archive.org/details/graftonpubliclibrary?sort=-publicdate.

If any residents or alumni have yearbooks from the missing years, we would love to borrow them to scan and digitize. We are missing 1955 and everything pre-1951 (except 1940) and would love to complete the collection. Yearbooks are sent via USPS with a tracking number directly to Boston Public Library and back. The process takes a few months, as many other libraries have digitization requests.

Library staff put out 108 bags for curbside pickup last week! Total curbside for October was 712 pickups. Call 508-839-4649 or email graftonlibrary.ma@gmail.com to request materials.

This week the Childrens Room put together 40 dino egg kits as a program to go. Each kit contains a dinosaur in a baking soda egg that can be hatched at home using vinegar, warm water, or simple tools.

Star Wars themed activity packets will go out December 1, coinciding with the start of our winter reading program. Register at www.graftonlibrary.org/wrp

The Library is still hosting virtual book groups for adults via Slack. This week, the Daytimers Book Group (3rd Tue at 1:30) discussed The Novel Diary by Richard Paul Evans and the Mystery Book Group (3rd Tue at 7:30) discussed The Hour of Death by Jane Willan.

Anyone interested in participating in those groups, or the “Not Just For Young Adults” Book Group, “Reads Well with Others” Book Group or the Inspirational Book Group is welcome. Efforts are made to get titles in as many different formats as possible (print, audio, large print, eAudio, eBook, etc.). Physical materials can be gotten through no-contact curbside pickup.  Digital materials are accessible through hoopladigital.com and cwmars.overdrive.com.

To attend the discussions via Slack, register at: https://join.slack.com/t/graftonpubliclibrary/shared_invite/zt-gevuyf4g-j3XtdeTQ8JSEUpI8GHItNQ

Then go to: http://graftonpubliclibrary.slack.com

To see upcoming book groups, go to the events page on the Grafton Public Library website at www.graftonlibrary.org/events

No comments

New Year’s at Noon Countdown Grab Bags

Posted by mcneilj on

Monday December 28, 2020 – Thursday December 31, 2020

Stop by the Library’s temporary location between 10AM and 4 PM to pick up a New Year’s Countdown Grab Bag.

Grab Bags contain a variety of seasonal activities and items to help the whole family celebrate 2021 together at home! One bag per family, please. While supplies last.

No comments

STEM Videos

Posted by mcneilj on

Have you watched all of our amazing STEM videos? Learn all about oil spills and crystals, and even learn how to design your own chicken coop in this series of video for kids in grades K-2 and grades 3-5.

 

Catch up now!

No comments

Weekly Report Nov 2-7

Posted by on

The Board of Library Trustees voted to waive fines for the duration of the pandemic – going forward, no new fines will accrue for Grafton items (two exceptions: equipment and museum passes). Please call 508-839-4649 if you currently have fines on your account. The Library traditionally goes fine-free every November and December and encourages patrons to donate the Grafton Food Bank in lieu of paying fines. They are hoping to do their gift card distribution next week, so time is of the essence for donations!

Fall reading programs are going well – 84 new registrations, 228 badges earned, and 730 books read. Watch for our Star Wars themes winter program which will begin Dec 1. Visit graftonlibrary.beanstack.com to participate.

We had 461 curbside pickups in September, added 558 new items and answered 475 reference questions. We delivered 7 items to four homebound patrons and made an outreach trip to Crescent Manor, delivering 47 items to nine patrons. There were 92 pickups last week, and on Halloween we plastic-bagged items to weatherproof them. We are strategizing how to handle the increasingly inclement weather.

Thanks to our library page Taylor who made sanitizing wipes since we can’t seem to purchase them anywhere.

We certified five senior work off volunteers through October 2020 – thanks to all who volunteered!

No comments

April Construction Report

Posted by on

The Library Planning and Building Committee met via Zoom on Monday April 6 and approved the following Change Orders:

  • Change order #8 $9750.10. Existing handrail in the front of the building is not AAB compliant. This was made as a requirement. John Stephens mentioned that the design of the handrail must be approved by the Grafton Historic Commission.  
  • Change order #9 $4500.00 credit for deletion of insulation.
  • Change order #10 $11729.08 for time and material work for soil testing. 
  • Change order #11 $ 2,873.85 for removal of an existing equipment pad in the mechanical room that was not documented and to avoid a trip hazard. 

Minutes are online at
https://www.grafton-ma.gov/sites/graftonma/files/minutes/library_planning_and_building_committee_minutes_04-06-2020.pdf

The construction team met Tuesday April 7, 14, 21, and 28 via conference call with CTA Construction, OPM, Clerk of the Works, and DRA Architects. 

We were advised on April 4 by MBLC that our project was not considered essential and we should take steps to shut down. We estimated about 2 weeks, but it turns out to shut the project down safely, we needed to take the following steps:

  • Complete excavation and backfill the hole.
  • Complete the removal of contaminated material per DEP/EPA regulations.
  • Ensure that the existing building is stable given the adjacent excavation.
  • Install some site drainage during this temporary condition so that the new building footprint stays protected while we’re shut down.

The goal is to have a complete shutdown of the project by May 12, 2020.

We don’t have a timetable on the impact of the shutdown at this point – it will depend on when the Governor re-starts construction projects across the state.

No comments

May Construction Report

Posted by on

The Library Planning and Building Committee met via Zoom on Monday May 4; minutes are online at
https://www.grafton-ma.gov/sites/graftonma/files/agendas/library_planning_and_building_committee_05-04-2020.pdf

The construction team met Tuesday May 5, 12, 19, and 26 via conference call with CTA Construction, OPM, Clerk of the Works, and DRA Architects. 

Our project made huge progress during the month of May – Please see photos on our Facebook page!

Construction: https://www.facebook.com/pg/GraftonPublicLibraryMA/photos/?tab=album&album_id=3005138386209267

Excavation: https://www.facebook.com/pg/GraftonPublicLibraryMA/photos/?tab=album&album_id=2840413639348410

Sitework

The site contractor has begun installing site drainage – pipe and structures.  We had a good call/review with the DOT, their review of the project will require that a new catch basin and drain manhole are added at the street, replacing the existing catch basin that is in poor condition. The parking lot area has been graded; 80% of the detention pond has been dug. It was determined that the area drain in front of the building will be held off the building by about 10’ in order to pull water away from the foundation. There will be waterproofing added to the interior face of the basement. The unintended benefit is that the majority of the gardens will now not be impacted. 

50% of the concrete building footings and 60% of the foundation walls have been completed. Concrete sleeves for water, sewer and electric have been placed in the foundation. 

The north gable end of the existing building had the surface brick removed where it had failed. It was determined that the backup brick had (unsurprisingly) also failed. We expect that masonry work to be completed in the next couple of weeks. Due to the high percentage of breakage when removing the bricks, the mason is going to be suggesting a matching brick to mix in with the old bricks that can be reused. This brick and mortar color will need to be reviewed by the Historic District Commission.

Some carpentry work has been done to the existing building including the addition of hurricane clips at the roof, the addition of a hatch entrance in the roof, and plywood for better attic access/safety. 

The GC has determined that there are no significant costs due to COVID-19 protocols. Unfortunately, the tonnage of site material removed is double the original estimate. There has been some over-excavation required for structural reasons; there were also 19 days of rain in April that added to the weight of the material being removed. It also seems like the original estimate was not accurate. 

Overall, work is on schedule – the biggest risk right now is the work that needs to be done at the 8.4 line which is where the old and new buildings come together.  Submittal review and approval has been good; RFI response times could be better (from a field perspective). The ‘shutdown’ for the State didn’t really slow the project down – our shutdown schedule pretty much ended when the mayor re-opened the Commonwealth.

There has been very good adherence to standard safety practices on site. A weekly safety review by an independent consulting company has been implement. COVID-19 protocols have been implemented and followed on site.

Additional consultants include:

  • A UTS representative has been on site to perform reviews of rebar and concrete. 
  • LGCI (geotechnical engineers) has been on site for any excavation to provide guidance on the structural quality of the bottom of the hole. Regular communication has occurred between LGCI, Derenzo, the Town and CTA whenever warranted. LGCI has submitted reports for the work when they’ve been on site. 
  • Weston & Sampson has been on site for groundwater monitoring well testing and to take soil samples from specific location around the excavation. 
  • MEP coordination has been ongoing and successful. There have been a few typical issues to be resolved but it is moving forward. 

 

 

 

 

No comments

June Construction Report

Posted by on

The Library Planning and Building Committee met via Zoom on Monday June 6; minutes are online at https://www.grafton-ma.gov/sites/g/files/vyhlif4461/f/minutes/library_planning_and_building_committee_minutes_06-01-2020.pdf

The construction team met Tuesday June 2, 9, 16, 23, and 30 via conference call with CTA Construction, OPM, Clerk of the Works, and DRA Architects.

Change orders from previous months are attached.

Over the last month, there was a lot of progress! Drainage (pipe and structures) is about 80% complete. Areas to be paved are 95% backfilled, compacted and to grade. Another! Underground Storage Tank (UST) was discovered approximately 8’ off of Upton Street adjacent to a telephone pole. It was removed and the impacted soil around it was tested and removed. Soil test results are pending.

No further concrete work has been done on the foundations but the new footings that are directly at the east face of the existing building are currently going in, after weeks of discussion and varying plans about how best to do this work.

Approximately half of the steel frame is erected, from column lines 1-5. The remainder will be in place in July. No significant issues, we have a good steel subcontractor.

The masonry work at the north gable end of the existing building has not yet been completed; an RFI associated with the work took a long time to be answered. The Historic District Commission approved the color of mortar to be used on the north gable end repairs. It may look a little light at first, but will age to match the existing building. The existing chimney was slated to have the top 6’ removed and due to the adjacent footing work starting now it was removed for safety purposes. The plaster walls in the basement have been removed. Underslab plumbing, Underground Tel/Data, site lighting conduits and underslab conduit are all scheduled to begin the week of 7/6/20.

Soil removal is nearly complete at this point so we’ll have a final tally on that massive change order in July. There have been a number of other PCOs generated that have been heavily reviewed, revised and combined into a Change Order for the committee’s review. The total for those PCOs is $155,027. As of the end of June, our contingency is at $765,699.

Work is on schedule – the key to maintaining the schedule was to get the steel erected so that masonry can begin on time. The work at 8.4 line took a long time to resolve and has held up foundations and steel but has not impacted the overall schedule. Submittal review and approval has been good; RFI response times could be better (from a field perspective). We are expecting to pave (binder course only) in the second week of August.

We have had very good adherence to standard safety practices on site, with a weekly safety review by independent consultant, and COVID-19 protocols in place and followed on site.

Our UTS representative has been on site to perform reviews of rebar and concrete and compaction testing of structural fill at roadways. LGCI (geotechnical engineers) has been on site for any excavation to provide guidance on the structural quality of the bottom of excavation. They will be involved in the work at 8.4 line. Weston & Sampson has been on site for groundwater monitoring well testing and to take soil samples from specific location around the excavation. The discovery of an additional UST was handled quickly by them including an additional filing with MA DEP. They are preparing a comprehensive report for the site which is required to be filed with the DEP in July.

We expect the mockup to be completed in July. The only remaining major item to be decided is the color of the siding — colonial yellow or pewter grey?

Check out photos in albums on our Facebook Page.

No comments

July Construction Report

Posted by on

The Library Planning and Building Committee met via Zoom on Monday July 6; minutes are online at
https://www.grafton-ma.gov/sites/g/files/vyhlif4461/f/minutes/library_planning_building_committee_minutes_07-06-2020.pdf

The Interiors sub-committee met Monday July 29.The construction team met Tuesday July 7, 14, 21 and 28 via conference call with CTA Construction, OPM, Clerk of the Works, and DRA Architects. 

Two Change Orders were issued: #11 for $8,908.58; #12 for $164,081.17; please see attached.

Two events are being planned: a topping off ceremony, and a beam signing (after beams are installed) for staff, trustees, friends, and the project team. 

The Capital Campaign brochure has been completed and printed.

Site drainage (pipe and structures) is complete with the exception of new DOT structures at the street.  Gabion walls are being constructed at the detention pond. 

A third Underground Storage Tank (UST) was discovered approximately 8’ off of Upton Street adjacent to a telephone pole. It was removed and the impacted soil around it was tested and removed.  Test pits at the front of the existing Library found buried brick and an unmarked rain leader but nothing else of significance. The rain leader (which runs to a dry well under the front lawn) will be replaced when perimeter drain work occurs in August. There is no more site excavation to be done! While soil excavation is complete, not all soil has been trucked from the site yet so final cost is not yet available. 

The remainder of the footings and foundation were poured. Concrete testing has occurred with every pour and results have been good.

The remainder of the steel began to be delivered and erected on Monday 7/27/20 and was completed on Friday 7/31/20. We expect the connections, deck and stud work to occur over the next two weeks.

The work at the north gable end of the existing building has been completed; the match of new bricks and mortar to the existing is excellent.  The masons are currently working on their portion of the on-site mockup.  

Additional structural angles have been installed at the lower level per the plans. 

Underslab plumbing is about 95% complete.  The underground Tel/Data run from the building to the pole at the street has been completed. Underslab electrical work will begin shortly now that the rest of the steel has been erected. 

There have been a number of smaller PCOs that have been combined into CO#12 for the committee’s review. Most of these were reviewed at the last committee meeting and have not changed significantly. The total for CO#12 is $176,538 . Our contingency is at $725,429. 

Work is on schedule – CTA’s overall schedule has been conservative to date and activities have taken less time. We are expecting to get a revised project schedule from them next week and get updates through the superintendent’s ‘Two Week Lookahead’ at every construction meeting. 

Submittals and RFIs are in good shape and should not have an impact on the schedule. 

We are expecting to pave (binder course only) in the second week of August along with light pole bases. 

There has been very good adherence to standard safety practices on site. Weekly safety review by an independent consultant has been occurring. COVID-19 protocol has been in place and followed on site. 

A UTS representative has been on site to perform reviews of rebar and concrete and compaction testing 

of structural fill at roadways. 

 

LGCI (geotechnical engineers) was on site for the underground work at 8.4 line (where the new and existing buildings meet). No issues. 

Weston & Sampson has been on site for groundwater monitoring well testing and to take soil samples from specific location around the excavation. The discovery of a third UST was handled quickly by them. Their RAM report to the DEP was completed and filed on time in July. Their turnaround time for soil samples has been slow and has caused some concern for the site contractor. 

The on-site mockup is still not completed; the masons were late returning to the site. We are working with CTA to get the rest of the mockup completed as soon as the masons are done so that the siding colors can be reviewed. 