Construction Update
The Library Planning and Building Committee met Sept 9 & 23. We selected a third party testing agent for the soil, concrete, and structural steel and are soliciting quotes for removal of the original (empty) oil tank. Schematics were revised and provided Sept 19 and are attached.

The Select Board voted to enter into a contract with CTA construction on Sept 3; the Notice to Award is attached.

The LULA was inspected for decommissioning. A walkthrough of the 35 Grafton Common property was scheduled.

Additional exterior lighting was added for the temporary facility.