Library Renovation and Expansion plans were approved by the Conservation Commission and by the Historic District Commission. Plans need to be approved by the MA Historical Commission, the Building Department, and Fire Marshall. We are in process of applying for a variance for ADA compliance from the MA Architectural Access Board. A more complete hazardous materials survey is scheduled for the 35 Grafton Common Building for July.

The Town has received a partial, advance grant disbursement of $460,000 from the Commonwealth of MA.

July MBLC Report
MHC Agreement
Central Register Bid

Building Committee Minutes
July 1, 2019

 